The OMB hearing on the Mary Lake Estates development application did begin as scheduled on April 15th. As negotiations, consistent with the resolution passed by Council on March 25, were still active the session was very brief and concluded with decision to reconvene April 18th. In the period before the 18th negotiations were completed and the OMB was advised that things were progressing to settlement but that it would take some days to complete the paperwork; accordingly all parties agreed to reconvene on Thursday April 25th at 10:30. In the interim Staff will be working with proponent to complete the draft plan of subdivision, the conditions of draft approval and the zoning bylaw.