On April 23 Council agenda there is a Staff recommendation for contractor to “fix” the 19th SDRD between Hwy 27 and Rebellion Way.  In an earlier post I reviewed alternatives to the initial recommendation to fully reconstruct the road.  At the November 13 meeting there was productive discussion, including deputations, which resulted in Council asking for pulverizing & resurfacing the road and replacing the culverts.  The contract being awarded at the 4/23 meeting is for $865,000 which is not only far less vs the initial proposal ($2.4 million) but importantly delivers a road format which is appropriate as the “country feel” of this stretch of the road including many trees will be retained.